In order to serve the growing market demands JANA is doubling production capacities of existing Epoxy production capability from 60,000 MTA to 120,000 MTA, this is achieved by putting up a new basic liquid resin line of 60,000 MTA and 2 solid reactors and 1 of solution by this, additional 22,000 MTA of Solid/Solution resin will be produced
Detailed engineering activities are currently being carried out by Technip and the completion is expected to be around end of March 2011.
The civil construction activities have begun in October 2010 by SBG contractor. In order to have better interface coordination and minimize the number of site contractors we have awarded the MEI contract to SBG. The contractor will commence the site work from February 2011..
The Project scheduled completion is March 2012 as originally and commissioning shall be completed by 2nd Quarter 2012.